How to Insulate Above a Concrete Floor Using SuperQuilt

Difficulty: Easy • 4 Steps

This guide will provide a step by step procedure to use SuperQuilt Insulation on Concrete Floors. SuperQuilt is proven to save on cost, space & installation time compared to Rigid PIR Insulation. PIR manufacturers include Kingspan & Celotex.

SuperQuilt is fully LABC & BDA certified for Solid Concrete Floors. The multi-layered blanket can commonly achieve building regulations stand-alone in floors. You can retrieve a U-value calculation in a PDF document which can be passed onto building control for acceptance. This can be downloaded by visiting our Free & Instant Online U-value Calculator – Click Here!

SuperQuilt’s LABC Certificate can be found at the following link – Click Here!

 

Multifoil-Insulation are the leading UK & European distributor of Multifoil Insulation products. We offer free next working day delivery to the UK Mainland (Order before 2pm)

Method Steps

  1. Installing first run of SuperQuilt

    SuperQuilt can be rolled out vertically or horizontally along the concrete floor. Leave enough material at the edges to protrude SuperQuilt Insulation above the floor deck. Ensure the concrete floor is fully clean, flat, and debris free.

  2. Joints and Taping

    Ensure SuperQuilt is butt jointed with other layers on both the verticals and horizontals. Fully tape and seal all butt joists of SuperQuilt with Thermaseal 75mm Foil Joining Tape.

  3. Installing Battens

    Timber battens or joists are then laid over the top of SuperQuilt. Ensure the timbers are spaced evenly to suit the particular flooring. SuperQuilt will compress to around 7mm when timber is installed above. We recommend min depth battens of 50mm, using 75 or 100mm joists/battens will give greater thermal benefits.

  4. Finish with Flooring

    Proceed with installing your timber boarding floor. The deck is then fixed at 200mm centres, with 37mm screws into the joists or battens below

Buy Tools & Materials

Disclaimer – SuperQuilt should be installed in harmony with the manufacturers certificate, fixing instructions and good building practice. Our Multifoils are to be cut using a craft knife or a sharp pair of scissors – Available in our Multifoil Fitting Kit. No personal protective equipment, clothing or handling is required.

Disclaimer – Multifoil-Insulation cannot be held responsible for any losses financially or physically from advice provided in this How-To-Guide.